DOB filing B00321519-I1
Alteration filing at 1485 Dumont Avenue
Building record · BIN 3096183
1485 Dumont Avenue, Brooklyn, NY 11208
A consolidated, filing-by-filing view of DOB records matched to this building identifier. The current snapshot links 4 independently sourced records, including 3 that are not recorded as completed, closed or withdrawn.
BUILDING RECORD · BIN 3096183
1485 Dumont Avenue
East New York-City Line, Brooklyn
A consolidated public-record view · updated Dec 3, 2021
A building-level summary of matched filings, active-status records and published identifiers.
What is recorded here
New York City's Building Identification Number helps connect filings that may use different application numbers or describe different scopes of work. The records below are grouped because they publish BIN 3096183. They should not be read as a single construction project unless the underlying filings say so.
The matched set includes 4 alteration filing. Its latest status categories are 3 approved, 1 recorded as completed. Each filing page preserves its own status, dates, scope and source identifier.
Highest recorded values may come from different filings and must not be combined into one proposed project. Open the individual filings below for their exact scope. Values outside the publication's conservative data-quality bounds are withheld pending source review.
Address alerts
Get an email when NewYorkDaily detects a material change in the public DOB records associated with 1485 Dumont Avenue.
Confirmation is required. Alerts describe source-data changes, not confirmed construction activity. Unsubscribe at any time. Privacy
Recorded history
Every dated event the city has published for this building, from all 4 matched filings, in the order it was recorded. A date marks what entered the public record, not what happened on site.
Combined heat and power installation w HW absorbers, cooling tower, boiler and associated mechanical work per plans. No change in use, egress or occupancy. The related permit under B00313620, B00314726, B00321519. Filing B00313620-I1.
Filing B00313620-I1 reached an approved status.
DOB lists a first permit date for B00313620-I1. That is not by itself confirmation of activity on site.
Combined heat and power installation w HW absorbers, cooling tower, boiler and associated mechanical work per plans. No change in use, egress or occupancy. The related permit under B00313620, B00314726, B00321519. Filing B00321519-I1.
Filing B00321519-I1 reached an approved status.
Combined heat and power installation w HW absorbers, cooling tower, boiler and associated mechanical work per plans. No change in use, egress or occupancy. The related permit under B00313620, B00314726, B00321519. Filing B00314726-I1.
Filing B00314726-I1 reached an approved status.
DOB lists a first permit date for B00314726-I1. That is not by itself confirmation of activity on site.
DOB lists a first permit date for B00321519-I1. That is not by itself confirmation of activity on site.
Installation of pipe scaffold as per plans. no change in use, egress or occupancy. Filing B00342573-I1.
Filing B00342573-I1 reached an approved status.
DOB lists a first permit date for B00342573-I1. That is not by itself confirmation of activity on site.
The latest status recorded for B00313620-I1 is “Permit Entire.”
The latest status recorded for B00314726-I1 is “Permit Entire.”
DOB recorded a sign-off for B00342573-I1.
The latest status recorded for B00342573-I1 is “LOC Issued.”
The latest status recorded for B00321519-I1 is “Permit Entire.”