DOB filing B00447308-S3
Alteration filing at 295 Jackson Street
Building record · BIN 3327832
295 Jackson Street, Brooklyn, NY 11211
A consolidated, filing-by-filing view of DOB records matched to this building identifier. The current snapshot links 20 independently sourced records, including 20 that are not recorded as completed, closed or withdrawn.
BUILDING RECORD · BIN 3327832
295 Jackson Street
East Williamsburg, Brooklyn
A consolidated public-record view · updated Sep 22, 2026
A building-level summary of matched filings, active-status records and published identifiers.
The lot
The lot holds a 8-story elevator apartment building built in 1950, with 700 homes, on a 510,960 sq ft lot.
Housing violations
11 violations are open against this address under the Housing Maintenance Code. 7 of them are the class the city calls immediately hazardous.
Open means the Department of Housing Preservation and Development has not recorded it as corrected, which is not the same as nobody having fixed it. The city publishes the apartment each was written against; that is not carried here, because a count says a building has a problem and an apartment number says whose.
Owner of record
NYC HOUSING AUTHORITY
As the assessment roll records it. Only owners that read as a company are shown here; where the roll names an individual, nothing is published.
Lot facts come from NYC Department of City Planning, Primary Land Use Tax Lot Output (PLUTO) (64uk-42ks), accessed Sep 25, 2026. They describe the tax lot, not any single filing. When the rest of New York went up
Violation record
The Department of Buildings has 1 open notice on record for this building, out of 16 notices on file; the most recent was issued Feb 22, 2023.
Issued Feb 22, 2023 — FAILED TO FILE FISP CYCLE 9B TECHNICAL REPORT BY 2/21/2023
Open means the agency has not recorded a resolution, which is not the same as the problem still existing. What a violation is, and what it is not. From NYC Department of Buildings, DOB Violations (3h2n-5cm9), accessed Sep 24, 2026.
What is recorded here
New York City's Building Identification Number helps connect filings that may use different application numbers or describe different scopes of work. The records below are grouped because they publish BIN 3327832. They should not be read as a single construction project unless the underlying filings say so.
The matched set includes 20 alteration filing. Its latest status categories are 19 approved, 1 under review. Each filing page preserves its own status, dates, scope and source identifier.
Highest recorded values may come from different filings and must not be combined into one proposed project. Open the individual filings below for their exact scope. Values outside the publication's conservative data-quality bounds are withheld pending source review.
Address alerts
Get an email when NewYorkDaily detects a material change in the public DOB records associated with 295 Jackson Street.
Confirmation is required. Alerts describe source-data changes, not confirmed construction activity. Unsubscribe at any time. Privacy
Recorded history
Every dated event the city has published for this building, from all 20 matched filings, in the order it was recorded. A date marks what entered the public record, not what happened on site.
Building 11-Removal of HW tank/heater, cold water supply & HW supply/return to tank.Install new gas DHW Htr,, HW re-circ pumps; new gas piping to DHW Htr; new hot & cold water supply/return piping to DHW Htr; install temp DHW Htr as shown on plans. Filing B00447246-I1.
Building 11-MH-Work in Tank room only- Demolition of steam and condensate piping, condensate pumps and vacuum pumps. Replacement of condensate pumps, vacuum pumps and piping. New flues for domestic hot water heaters. All as per plans filed herewith. Filing B00447308-I1.
Filing B00447308-I1 reached an approved status.
Building 11-provide loose lintel for louver opening on masonry wall; repair concrete pad; provide boiler access platform; provide outdoor enclosure support framing. Filing B00447308-S1.
Filing B00447308-S1 reached an approved status.
Bldg 11 - Proposed Boiler application filed to replace 3 existing dual fuel boilers (Oil/Gas) with new GAS boiler. Boiler #4 will be removed as per plans. Original filing does not allow us to update the energy source of existing or of NEW boilers. Filing B00447355-I1.
Filing B00447355-I1 reached an approved status.
Filing B00447246-I1 reached an approved status.
NYCHA Boiler - Building 11 - Civil General Construction work to include underground fuel oil tank removal. All as per plans filed herewith. Filing B00447308-S3.
NYCHA Boiler - Building 11 - Civil PL- Natural Gas piping will be run above-ground from gas meter enclosure and domestic hot water heater rooms. Filing B00447308-S2.
Filing B00447308-S3 reached an approved status.
Filing B00447308-S2 reached an approved status.
NYCHA BLDG #11- Architectural work being filed in conjunction with Cooper Houses and all related applications. All as per plans filed herewith. Filing B00447308-S4.
Filing B00447308-S4 reached an approved status.
Building 11-Work in Tank room only- Demolition of steam and condensate piping, condensate pumps and vacuum pumps. Replacement of condensate pumps, vacuum pumps and piping. New flues for domestic hot water heaters. Filing B00447308-P1.
Filing B00447308-P1 reached an approved status.
The latest status recorded for B00447308-P1 is “Approved.”
DOB lists a first permit date for B00447308-S4. That is not by itself confirmation of activity on site.
DOB lists a first permit date for B00447308-S1. That is not by itself confirmation of activity on site.
DOB lists a first permit date for B00447308-S3. That is not by itself confirmation of activity on site.
Building 11-Demolition of existing hot water tank, cold & hot water supply/return to the tank. Install new gas water heaters, expansion tank, hot water recirculation pumps & associated valves in tank/boiler room. Install temporary water heaters. Filing B00447246-P1.
Filing B00447246-P1 reached an approved status.
The latest status recorded for B00447246-P1 is “Approved.”
DOB lists a first permit date for B00447246-I1. That is not by itself confirmation of activity on site.
Building 11-Work in Tank room only- Demolition of steam and condensate piping, condensate pumps and vacuum pumps. Replacement of condensate pumps, vacuum pumps and piping. New flues for domestic hot water heaters. Filing B00447308-P2.
DOB lists a first permit date for B00447308-I1. That is not by itself confirmation of activity on site.
Filing B00447308-P2 reached an approved status.
The latest status recorded for B00447308-P2 is “Approved.”
Building 11-MH-Work in Tank room only- Demolition of steam and condensate piping, condensate pumps and vacuum pumps. Replacement of condensate pumps, vacuum pumps and piping. New flues for domestic hot water heaters. All as per plans filed herewith. Filing B00447308-P5.
Building 11-Removal of existing hot water tank, cold & hot water supply/return to the tank. Install new gas water heaters, expansion tank, hot water re-circulation pumps & associated valves in tank/boiler room. Install temporary water heaters. Filing B00447246-P2.
NYCHA Boiler - Building 11 - Civil PL- Natural Gas piping will be run above-ground from gas meter enclosure and domestic hot water heater rooms. Filing B00447308-P4.
NYCHA Boiler - Building 11 - Civil General Construction work to include underground fuel oil tank removal. All as per plans filed herewith. Filing B00447308-P3.
The latest status recorded for B00447355-I1 is “Approved.”
Bldg 11 - Proposed Boiler application filed to replace 3 existing dual fuel boilers (Oil/Gas) with new GAS boiler. Boiler #4 will be removed as per plans. Original filing does not allow us to update the energy source of existing or of NEW boilers. Filing B00447355-P1.
Filing B00447355-P1 reached an approved status.
The latest status recorded for B00447355-P1 is “Approved.”
Filing B00447308-P5 reached an approved status.
The latest status recorded for B00447308-P5 is “Approved.”
Filing B00447308-P4 reached an approved status.
The latest status recorded for B00447308-P4 is “Approved.”
Filing B00447246-P2 reached an approved status.
The latest status recorded for B00447246-P2 is “Approved.”
Filing B00447308-P3 reached an approved status.
The latest status recorded for B00447308-P3 is “Approved.”
Building 11-Removal of HW tank/heater, cold water supply & HW supply/return to tank.Install new gas DHW Htr,, HW re-circ pumps; new gas piping to DHW Htr; new hot & cold water supply/return piping to DHW Htr; install temp DHW Htr as shown on plans. Filing B00447246-P3.
Filing B00447246-P3 reached an approved status.
The latest status recorded for B00447246-P3 is “Approved.”
NYCHA BLDG #11- Architectural work being filed in conjunction with Cooper Houses and all related applications. All as per plans filed herewith. Filing B00447308-P6.
Filing B00447308-P6 reached an approved status.
The latest status recorded for B00447308-P6 is “Approved.”
NYCHA BLDG #11- Architectural work being filed in conjunction with Cooper Houses and all related applications. All as per plans filed herewith. Filing B00447308-P7.
Filing B00447308-P7 reached an approved status.
The latest status recorded for B00447308-P7 is “Approved.”
Building 11-provide loose lintel for louver opening on masonry wall; repair concrete pad; provide boiler access platform; provide outdoor enclosure support framing. Filing B00447308-P8.
Filing B00447308-P8 reached an approved status.
The latest status recorded for B00447308-P8 is “Approved.”
The latest status recorded for B00447246-I1 is “Permit Entire.”
The latest status recorded for B00447308-I1 is “Permit Entire.”
The latest status recorded for B00447308-S1 is “Permit Entire.”
The latest status recorded for B00447308-S4 is “Permit Entire.”
Building 11-Removal of HW tank/heater, cold water supply & HW supply/return to tank.Install new gas DHW Htr,, HW re-circ pumps; new gas piping to DHW Htr; new hot & cold water supply/return piping to DHW Htr; install temp DHW Htr as shown on plans. Filing B00447246-P4.
The latest status recorded for B00447246-P4 is “Objections.”
The latest status recorded for B00447308-S3 is “Permit Entire.”
The latest status recorded for B00447308-S2 is “Approved.”