Building record · BIN 3328042

370 Blake Avenue

370 Blake Avenue, Brooklyn, NY 11212

A consolidated, filing-by-filing view of DOB records matched to this building identifier. The current snapshot links 8 independently sourced records, including 4 that are not recorded as completed, closed or withdrawn.

Open full map
newyorkdailyStreet Futures

BUILDING RECORD · BIN 3328042

370 Blake Avenue

Brownsville, Brooklyn

A consolidated public-record view · updated Aug 31, 2026

DOB filings
8
Active-status
4
Recorded addresses
2
Building data portrait

A building-level summary of matched filings, active-status records and published identifiers.

Matched filings8
Open or active-status records4
First included filingDec 3, 2019
Latest recorded changeAug 31, 2026

The lot

What is already here?

The lot holds a 14-story elevator apartment building built in 1958, with 525 homes, on a 305,266 sq ft lot.

  1. Floors 2–14Homes525 homes are recorded on this lot — about 40 homes to a floor. The city does not publish which floor any of them is on.
  2. Floor 1Street levelStreet level. The lot is recorded as elevator apartments.
  • Street levelElevator apartments
  • Homes525 recorded on the lot
  • Above the southern skylineFrom about floor 16 — the tallest thing within 60 m to the south is 45.9 m
Drawn from the outline and roof height the Department of City Planning publishes for this building: 43 m over 14 floors, as the city counts them. 2 runs of floors have something on record. The city publishes a roof height and a storey count for the lot, and nothing at all about any individual floor. What stands to the south is measured from the city’s own footprints and roof heights; it is a statement about the skyline, not a calculation of sunlight.
Built
1958
Floors
14
Residential units
525
Building type
Elevator apartment building
Land use
Elevator apartments
Zoning district
R6
Lot area
305,266 sq ft
Building area
451,586 sq ft

Housing violations

3 violations are open against this address under the Housing Maintenance Code.

  • 0Immediately hazardous
  • 2Hazardous
  • 1Non-hazardous
  • 0Information order

Open means the Department of Housing Preservation and Development has not recorded it as corrected, which is not the same as nobody having fixed it. The city publishes the apartment each was written against; that is not carried here, because a count says a building has a problem and an apartment number says whose.

Owner of record

NYC HOUSING AUTHORITY

As the assessment roll records it. Only owners that read as a company are shown here; where the roll names an individual, nothing is published.

Lot facts come from NYC Department of City Planning, Primary Land Use Tax Lot Output (PLUTO) (64uk-42ks), accessed Sep 21, 2026. They describe the tax lot, not any single filing. When the rest of New York went up

Violation record

Are there open violations here?

The Department of Buildings has 3 open notices on record for this building, out of 11 notices on file; the most recent was issued Feb 22, 2023.

  • No report and / or late filing (facade)

    Issued Feb 22, 2023 — FAILED TO FILE FISP CYCLE 9B TECHNICAL REPORT BY 2/21/2023

  • Facade safety program

    Issued Feb 7, 2020

  • Public

    Issued Aug 2, 1989

Open means the agency has not recorded a resolution, which is not the same as the problem still existing. What a violation is, and what it is not. From NYC Department of Buildings, DOB Violations (3h2n-5cm9), accessed Sep 21, 2026.

What is recorded here

Multiple filings, one stable building identifier.

New York City's Building Identification Number helps connect filings that may use different application numbers or describe different scopes of work. The records below are grouped because they publish BIN 3328042. They should not be read as a single construction project unless the underlying filings say so.

The matched set includes 8 alteration filing. Its latest status categories are 4 recorded as completed, 4 approved. Each filing page preserves its own status, dates, scope and source identifier.

First included filing
Dec 3, 2019
Latest recorded change
Aug 31, 2026
Highest proposed story count
14 stories
Highest proposed unit count
150 dwelling units

Highest recorded values may come from different filings and must not be combined into one proposed project. Open the individual filings below for their exact scope. Values outside the publication's conservative data-quality bounds are withheld pending source review.

Address alerts

Watch this address.

Get an email when NewYorkDaily detects a material change in the public DOB records associated with 370 Blake Avenue.

Confirmation is required. Alerts describe source-data changes, not confirmed construction activity. Unsubscribe at any time. Privacy

Recorded history

What has happened at this address?

Every dated event the city has published for this building, from all 8 matched filings, in the order it was recorded. A date marks what entered the public record, not what happened on site.

  1. Alteration filed

    Installation of new sidewalk shed at 372 blake avenue, brooklyn as indicated on plans. there will be no change in the use, egress, or occupancy under this application. Filing B00273527-I1.

    01
  2. Alteration filed

    Installation of temporary construction fence at 372 blake avenue, brooklyn as indicated on plans. there will be no change in the use, egress, or occupancy under this application. Filing B00273587-I1.

    02
  3. Permit recorded for alteration

    DOB lists a first permit date for B00273527-I1. That is not by itself confirmation of activity on site.

    03
  4. Permit recorded for alteration

    DOB lists a first permit date for B00273587-I1. That is not by itself confirmation of activity on site.

    04
  5. Alteration filed

    Nycha boiler: mechanical work for central boiler plant and domestic hot water system replacement (van dyke bldg #11) as per the plans filed herewith. Filing B00462728-I1.

    05
  6. Alteration filed

    Plumbing work as per plans filed herewith. no change to use, egress or occupancy. Filing B00463348-I1.

    06
  7. Alteration approved

    Filing B00463348-I1 reached an approved status.

    07
  8. Alteration filed

    "nycha boiler" general construction as per plans filed herewith. no change to use, egress, or occupancy. Filing B00456662-I1.

    08
  9. Alteration approved

    Filing B00456662-I1 reached an approved status.

    09
  10. Alteration filed

    Nycha boiler-structrual work in the cellar floor as per plans filed herewith. no change in use, egress or occupancy. Filing B00460588-I1.

    010
  11. Alteration filed

    Plumbing work as per plans filed herewith. no change to use, egress or occupancy. Filing B00463348-P1.

    011
  12. Alteration approved

    Filing B00463348-P1 reached an approved status.

    012
  13. Alteration now approved

    The latest status recorded for B00463348-P1 is “Approved.”

    013
  14. Alteration approved

    Filing B00462728-I1 reached an approved status.

    014
  15. Alteration approved

    Filing B00460588-I1 reached an approved status.

    015
  16. Permit recorded for alteration

    DOB lists a first permit date for B00462728-I1. That is not by itself confirmation of activity on site.

    016
  17. Permit recorded for alteration

    DOB lists a first permit date for B00456662-I1. That is not by itself confirmation of activity on site.

    017
  18. Permit recorded for alteration

    DOB lists a first permit date for B00463348-I1. That is not by itself confirmation of activity on site.

    018
  19. Permit recorded for alteration

    DOB lists a first permit date for B00460588-I1. That is not by itself confirmation of activity on site.

    019
  20. Alteration signed off

    DOB recorded a sign-off for B00273527-I1.

    020
  21. Alteration now completed

    The latest status recorded for B00273527-I1 is “LOC Issued.”

    021
  22. Alteration signed off

    DOB recorded a sign-off for B00273587-I1.

    022
  23. Alteration now completed

    The latest status recorded for B00273587-I1 is “LOC Issued.”

    023
  24. Alteration now approved

    The latest status recorded for B00460588-I1 is “Permit Entire.”

    024
  25. Alteration filed

    Plumbing work as per plans filed herewith. no change to use, egress or occupancy. Filing B00463348-P2.

    025
  26. Alteration now approved

    The latest status recorded for B00463348-I1 is “Permit Entire.”

    026
  27. Alteration approved

    Filing B00463348-P2 reached an approved status.

    027
  28. Alteration now approved

    The latest status recorded for B00463348-P2 is “Approved.”

    028
  29. Alteration signed off

    DOB recorded a sign-off for B00456662-I1.

    029
  30. Alteration now completed

    The latest status recorded for B00456662-I1 is “LOC Issued.”

    030
  31. Alteration signed off

    DOB recorded a sign-off for B00462728-I1.

    031
  32. Alteration now completed

    The latest status recorded for B00462728-I1 is “LOC Issued.”

    032