DOB filing B00236737-I1
Alteration filing at 530 President Street
Building record · BIN 3424497
530 President Street, Brooklyn, NY 11215
A consolidated, filing-by-filing view of DOB records matched to this building identifier. The current snapshot links 4 independently sourced records, including 1 that are not recorded as completed, closed or withdrawn.
BUILDING RECORD · BIN 3424497
530 President Street
Carroll Gardens-Cobble Hill-Gowanus-Red Hook, Brooklyn
A consolidated public-record view · updated May 26, 2022
A building-level summary of matched filings, active-status records and published identifiers.
What is recorded here
New York City's Building Identification Number helps connect filings that may use different application numbers or describe different scopes of work. The records below are grouped because they publish BIN 3424497. They should not be read as a single construction project unless the underlying filings say so.
The matched set includes 4 alteration filing. Its latest status categories are 3 recorded as completed, 1 approved. Each filing page preserves its own status, dates, scope and source identifier.
Highest recorded values may come from different filings and must not be combined into one proposed project. Open the individual filings below for their exact scope. Values outside the publication's conservative data-quality bounds are withheld pending source review.
Address alerts
Get an email when NewYorkDaily detects a material change in the public DOB records associated with 530 President Street.
Confirmation is required. Alerts describe source-data changes, not confirmed construction activity. Unsubscribe at any time. Privacy
Recorded history
Every dated event the city has published for this building, from all 4 matched filings, in the order it was recorded. A date marks what entered the public record, not what happened on site.
Alt 2 for installation of new 60,000 btu split system air conditioning system only. No change of use, occupancy, egress or bulk. Filing B00201415-I1.
Filing B00201415-I1 reached an approved status.
Installation of new emergency generator on the roof level.mechanical work. no change in use, occupancy or egress. Filing B00236737-I1.
Installation of dunnage at roof level, work filed in conjunction with installation of new emergency generator on the roof level. no change in use,occupancy or egress. Filing B00236727-I1.
Filing B00236727-I1 reached an approved status.
Filing B00236737-I1 reached an approved status.
DOB lists a first permit date for B00236737-I1. That is not by itself confirmation of activity on site.
DOB lists a first permit date for B00236727-I1. That is not by itself confirmation of activity on site.
DOB lists a first permit date for B00201415-I1. That is not by itself confirmation of activity on site.
Alt 2 for installation of new 60,000 btu split system air conditioning system only. No change of use, occupancy, egress or bulk. Filing B00201415-P1.
Filing B00201415-P1 reached an approved status.
The latest status recorded for B00201415-P1 is “Approved.”
DOB recorded a sign-off for B00236727-I1.
The latest status recorded for B00236727-I1 is “LOC Issued.”
DOB recorded a sign-off for B00201415-I1.
The latest status recorded for B00201415-I1 is “LOC Issued.”
DOB recorded a sign-off for B00236737-I1.
The latest status recorded for B00236737-I1 is “LOC Issued.”