DOB filing B00358540-I1
Alteration filing at 2 Blue Slip
Building record · BIN 3428938
2 Blue Slip, Brooklyn, NY 11222
A consolidated, filing-by-filing view of DOB records matched to this building identifier. The current snapshot links 6 independently sourced records, including 1 that are not recorded as completed, closed or withdrawn.
BUILDING RECORD · BIN 3428938
2 Blue Slip
Greenpoint, Brooklyn
A consolidated public-record view · updated Jun 2, 2021
A building-level summary of matched filings, active-status records and published identifiers.
What is recorded here
New York City's Building Identification Number helps connect filings that may use different application numbers or describe different scopes of work. The records below are grouped because they publish BIN 3428938. They should not be read as a single construction project unless the underlying filings say so.
The matched set includes 6 alteration filing. Its latest status categories are 5 recorded as completed, 1 approved. Each filing page preserves its own status, dates, scope and source identifier.
Highest recorded values may come from different filings and must not be combined into one proposed project. Open the individual filings below for their exact scope. Values outside the publication's conservative data-quality bounds are withheld pending source review.
Address alerts
Get an email when NewYorkDaily detects a material change in the public DOB records associated with 2 Blue Slip.
Confirmation is required. Alerts describe source-data changes, not confirmed construction activity. Unsubscribe at any time. Privacy
Recorded history
Every dated event the city has published for this building, from all 6 matched filings, in the order it was recorded. A date marks what entered the public record, not what happened on site.
Installation of scaffold as per drawings. scaffold shall comply with chapter #33 of the NYC building code. no change in use, occupancy or egress under this application. Filing B00062925-I1.
DOB lists a first permit date for B00062925-I1. That is not by itself confirmation of activity on site.
Installation of pipe scaffold as per plans. no change in use, egress or occupancy. Filing B00162643-I1.
DOB lists a first permit date for B00162643-I1. That is not by itself confirmation of activity on site.
DOB recorded a sign-off for B00162643-I1.
Installation of equipment and ducts as shown on plans. Filing B00358540-I1.
Relocation, removal and installation of new sprinkler heads and relocation of piping. Filing B00358530-I1.
Filing B00358530-I1 reached an approved status.
Filing B00358540-I1 reached an approved status.
Modification of plumbing system as shown on plans. Filing B00377121-I1.
Filing B00377121-I1 reached an approved status.
DOB lists a first permit date for B00358540-I1. That is not by itself confirmation of activity on site.
DOB lists a first permit date for B00358530-I1. That is not by itself confirmation of activity on site.
DOB lists a first permit date for B00377121-I1. That is not by itself confirmation of activity on site.
DOB recorded a sign-off for B00062925-I1.
The latest status recorded for B00062925-I1 is “LOC Issued.”
The latest status recorded for B00162643-I1 is “LOC Issued.”
DOB recorded a sign-off for B00377121-I1.
The latest status recorded for B00377121-I1 is “LOC Issued.”
DOB recorded a sign-off for B00358530-I1.
The latest status recorded for B00358530-I1 is “LOC Issued.”
Installation of equipment and ducts as shown on plans. Filing B00358540-P1.
Filing B00358540-P1 reached an approved status.
The latest status recorded for B00358540-P1 is “Approved.”
DOB recorded a sign-off for B00358540-I1.
The latest status recorded for B00358540-I1 is “LOC Issued.”