What the filing says
A public-record reading of the proposed work.
Installation of shoring for column 62 and column 63 between floor 21 and floor 22. installation of seat catch system on column 57 and column 58 on multiple floors. cut and remove column 62 and column 63 on floor 21. installation of jacking assemblies in p
Street Futures classifies this record as a alteration filing based on the filing type and work flags published by the Department of Buildings. This classification helps organize the map; it does not add scope that is absent from the DOB record.
The lot this filing sits on
What is already here?
The lot holds a 37-story elevator apartment building built in 1960, with 884 homes, on a 37,657 sq ft lot.
- Built
- 1960
- Last altered
- 2025
- Floors
- 37
- Residential units
- 884
- Building type
- Elevator apartment building
- Land use
- Mixed residential and commercial
- Zoning district
- C5-3
- Lot area
- 37,657 sq ft
- Building area
- 728,739 sq ft
Lot facts come from NYC Department of City Planning, Primary Land Use Tax Lot Output (PLUTO) (64uk-42ks), accessed Sep 15, 2026. They describe the tax lot, not this filing.
Violation record
Are there open violations here?
The Department of Buildings has 28 open notices on record for this building, out of 166 notices on file; the most recent was issued Sep 1, 2026.
- Construction
Issued Sep 1, 2026 — STEEL HIGH-RISE UNDER ALT. W/ SIGNIFICANT DAMAGE & DEFORMATION.COLS 62&63 EXHIBITED SIGNS OF FAILURE, FL 21-22. COL REMOVAL UNDER M011442594. ADD'L INFO REQ'D.REMEDY:LABEL & MAINTAIN ALL PIECES ON SITE.SUBMIT DIAGRAM.OBTAIN DOB APPROVAL PRIOR TO TESTING OR REMOVING
- Construction
Issued Jul 9, 2026 — SHOP DWGS - STEEL HIGH-RISE UNDER PERMITTED ALT. COLUMNS BUCKLING FL 21-22. REMEDY:SUBMIT APPROVED/ACCEPTED STEEL SHOP DRAWINGS BY 7/16/26
- Construction
Issued Jul 9, 2026 — STEEL HIGH-RISE UNDER PERMITTED ALT. WITH SEVERE DAMAGE,DEFORMATION & COLLAPSE RISK.COLUMNS BUCKLING FL 21-22. REMEDY:RETAIN SIA TO INSPECT STRUCTURAL WORK SPECIFIED BY DESIGN APPLICANT AND APPROVED/ACCEPTED DOCUMENTS
25 further open notices are on file. Open the source dataset for the full list.
Open means the agency has not recorded a resolution, which is not the same as the problem still existing. What a violation is, and what it is not. From NYC Department of Buildings, DOB Violations (3h2n-5cm9), accessed Sep 13, 2026.
Recorded timeline
Dates published by the Department of Buildings.
- Application filed01
DOB received filing M01442594-I1.
- Application approved02
The application reached an approved status in the DOB record.
- First permit date recorded03
DOB lists a first permit date. This does not by itself confirm current construction activity.
- Current status updated04
The latest recorded filing status is “Permit Entire.”
For scale: half of DOB filings are permitted within 20 days of being filed and a quarter take longer than 4 months, measured across 62,630 filings that carry both dates. How long a permit takes, by work type and borough
Scope and identifiers
The details used to match this filing.
Where a field reads “empty in the source”, the city published this filing without that value. It is not an omission on our side, and nothing here is inferred to fill a gap.
- DOB filing number
- M01442594-I1
- BBL
- 1013160023
- Postal code
- 10017 · 398 filings
- Review type
- Standard Plan Examination
- Existing stories
- 33
- Proposed stories
- 37
- Existing dwelling units
- 0
- Proposed dwelling units
- 927