DOB filing B00611202-S6
New building at 340 Nevins Street
Building record · BIN 3430358
340 Nevins Street, Brooklyn, NY 11215
A consolidated, filing-by-filing view of DOB records matched to this building identifier. The current snapshot links 20 independently sourced records, including 19 that are not recorded as completed, closed or withdrawn.
A building-level summary of matched filings, active-status records and published identifiers.
The lot
The lot holds a 17-story elevator apartment building built in 2024, with 654 homes, on a 51,445 sq ft lot.
Lot facts come from NYC Department of City Planning, Primary Land Use Tax Lot Output (PLUTO) (64uk-42ks), accessed Sep 2, 2026. They describe the tax lot, not any single filing.
What is recorded here
New York City's Building Identification Number helps connect filings that may use different application numbers or describe different scopes of work. The records below are grouped because they publish BIN 3430358. They should not be read as a single construction project unless the underlying filings say so.
The matched set includes 20 new building. Its latest status categories are 19 approved, 1 recorded as completed. Each filing page preserves its own status, dates, scope and source identifier.
Highest recorded values may come from different filings and must not be combined into one proposed project. Open the individual filings below for their exact scope. Values outside the publication's conservative data-quality bounds are withheld pending source review.
Address alerts
Get an email when NewYorkDaily detects a material change in the public DOB records associated with 340 Nevins Street.
Confirmation is required. Alerts describe source-data changes, not confirmed construction activity. Unsubscribe at any time. Privacy
Recorded history
Every dated event the city has published for this building, from all 20 matched filings, in the order it was recorded. A date marks what entered the public record, not what happened on site.
Filing to erect a new 22 story mixed use building (building B). Affordable housing. HUB consultation accepted on 9/21/21 (300 Nevins St). This NB is located within the Gowanus rezoning area & is pursuing FO approval/permit . Related NB B00611166-I1. Filing B00611202-I1.
Foundation work in conjunction with NB B00611202-I1 Affordable housing. HUB consultation accepted 9/21/21 (300 Nevins St). This NB is located within the Gowanus rezoning area & is pursuing FO approval/permit for 421A. Related NB Building A B00611166-I1. Filing B00611202-S1.
Structural work in conjunction with NB B00611202-I1 Affordable housing. HUB consultation accepted 9/21/21 (300 Nevins St). This NB is located within the Gowanus rezoning area & is pursuing FO approval/permit for 421A. Related NB Building A B00611166-I1. Filing B00611202-S2.
Filing B00611202-S2 reached an approved status.
Mechanical work in conjunction with NB B00611202-I1 (Building B). Affordable housing. HUB consultation accepted on 9/21/21 (300 Nevins St). Filing B00611202-S3.
Plumbing work in conjunction with NB B00611202-I1 (Building B). Affordable housing. HUB consultation accepted on 9/21/21 (340 Nevins St). Filing B00611202-S4.
Filing B00611202-S1 reached an approved status.
DOB lists a first permit date for B00611202-S1. That is not by itself confirmation of activity on site.
Single foundation element filed in conjunction with NB B00611202-I1. Filing B00611202-S6.
Filing B00611202-S6 reached an approved status.
DOB lists a first permit date for B00611202-S6. That is not by itself confirmation of activity on site.
Pile installation only filed in conjunction with new building B00611202-I1, balance of foundation work filed under B00611202-S1. Filing B00611202-S8.
Filing B00611202-S8 reached an approved status.
New installation of combined sprinkler and standpipe system as shown on plans, Filed in conjuction with New Building B00611202-I1. Filing B00611202-S7.
Installation of temporary air-pressurized alarm system for dry standpipe system during construction. filed in conjunction with nb# b00611202-i1. Filing B00611202-S9.
Filing B00611202-S9 reached an approved status.
Filing B00611202-S7 reached an approved status.
DOB lists a first permit date for B00611202-S8. That is not by itself confirmation of activity on site.
Filing B00611202-I1 reached an approved status.
Filing B00611202-S4 reached an approved status.
DOB lists a first permit date for B00611202-S4. That is not by itself confirmation of activity on site.
DOB lists a first permit date for B00611202-S2. That is not by itself confirmation of activity on site.
DOB lists a first permit date for B00611202-S9. That is not by itself confirmation of activity on site.
Filing B00611202-S3 reached an approved status.
DOB lists a first permit date for B00611202-S3. That is not by itself confirmation of activity on site.
DOB lists a first permit date for B00611202-I1. That is not by itself confirmation of activity on site.
This subsequent document is administrative in nature in order to be able to obtain COC's in DOBNOW for mechanical units. All work/floor plans are submitted under the main MS filing B00611202-S3. Filing B00611202-Z2.
Filing B00611202-Z2 reached an approved status.
On site storm drainage system for South building including drains, manholes and hydrodynamic separators discharging to new outfalls to Gowanus Canal. North building filed separately under B00611166-Z1. Filing B00611202-Z1.
Filing B00611202-Z1 reached an approved status.
DOB lists a first permit date for B00611202-S7. That is not by itself confirmation of activity on site.
DOB lists a first permit date for B00611202-Z1. That is not by itself confirmation of activity on site.
The latest status recorded for B00611202-Z1 is “Permit Entire.”
Structural work for new elevated walkway in conjunction with NB. Filing B00611202-Z5.
Foundation work relating to elevated walkway in conjunction with NB. Filing B00611202-Z4.
Filing B00611202-Z5 reached an approved status.
Plumbing work in conjunction with NB B00611202-I1 (Building B). Affordable housing. HUB consultation accepted on 9/21/21 (300 Nevins St). Filing B00611202-A2.
Filing B00611202-A2 reached an approved status.
The latest status recorded for B00611202-A2 is “Approved.”
DOB lists a first permit date for B00611202-Z2. That is not by itself confirmation of activity on site.
Filing B00611202-Z4 reached an approved status.
The latest status recorded for B00611202-S8 is “Permit Entire.”
Landscaping for outdoor walkway. Filing B00611202-Z7.
DOB lists a first permit date for B00611202-Z4. That is not by itself confirmation of activity on site.
The latest status recorded for B00611202-Z4 is “Permit Entire.”
DOB lists a first permit date for B00611202-Z5. That is not by itself confirmation of activity on site.
The latest status recorded for B00611202-Z5 is “Permit Entire.”
Filing B00611202-Z7 reached an approved status.
The latest status recorded for B00611202-Z7 is “Approved.”
Filing to erect a new 22 story mixed use building (building B). Affordable housing. HUB consultation accepted on 9/21/21 (300 Nevins St). This NB is located within the Gowanus rezoning area & is pursuing FO approval/permit . Related NB B00611166-I1. Filing B00611202-A4.
New installation of combined sprinkler and standpipe system as shown on plans, Filed in conjuction with New Building B00611202-I1. Filing B00611202-A5.
The latest status recorded for B00611202-Z2 is “Permit Entire.”
Filing B00611202-A4 reached an approved status.
The latest status recorded for B00611202-A4 is “Approved.”
Mechanical work in conjunction with NB B00611202-I1 (Building B). Affordable housing. HUB consultation accepted on 9/21/21 (300 Nevins St). Filing B00611202-A3.
Plumbing work in conjunction with NB B00611202-I1 (Building B). Affordable housing. HUB consultation accepted on 9/21/21 (340 Nevins St). Filing B00611202-A6.
The latest status recorded for B00611202-S3 is “Permit Entire.”
Filing B00611202-A3 reached an approved status.
The latest status recorded for B00611202-A3 is “Approved.”
The latest status recorded for B00611202-S4 is “Permit Entire.”
Filing B00611202-A6 reached an approved status.
The latest status recorded for B00611202-A6 is “Approved.”
The latest status recorded for B00611202-S7 is “Permit Entire.”
Filing B00611202-A5 reached an approved status.
The latest status recorded for B00611202-A5 is “Approved.”
The latest status recorded for B00611202-I1 is “Permit Entire.”
Single foundation element filed in conjunction with NB B00611202-I1. Filing B00611202-A7.
DOB recorded a sign-off for B00611202-S9.
The latest status recorded for B00611202-S9 is “LOC Issued.”
Filing B00611202-A7 reached an approved status.
The latest status recorded for B00611202-A7 is “Approved.”
The latest status recorded for B00611202-S1 is “Permit Entire.”
The latest status recorded for B00611202-S2 is “Permit Entire.”
The latest status recorded for B00611202-S6 is “Permit Entire.”