What the filing says
A public-record reading of the proposed work.
Application filed for temporary shoring to support beams per plans filed herewith. Filed in conjunction with Alt CO M01084591.
Street Futures classifies this record as a alteration filing based on the filing type and work flags published by the Department of Buildings. This classification helps organize the map; it does not add scope that is absent from the DOB record.
The lot this filing sits on
What is already here?
The lot holds a 31-story elevator apartment building built in 1961, with 788 homes, on a 33,340 sq ft lot.
- Built
- 1961
- Last altered
- 2013
- Floors
- 31
- Residential units
- 788
- Building type
- Elevator apartment building
- Land use
- Elevator apartments
- Zoning district
- C5-5
- Lot area
- 33,340 sq ft
- Building area
- 762,175 sq ft
Lot facts come from NYC Department of City Planning, Primary Land Use Tax Lot Output (PLUTO) (64uk-42ks), accessed Sep 25, 2026. They describe the tax lot, not this filing.
Violation record
Are there open violations here?
The Department of Buildings has 5 open notices on record for this building, out of 224 notices on file; the most recent was issued Aug 4, 2026.
- Construction
Issued Aug 4, 2026 — EMERGENCY WORK:STRUCTURAL CRACKING OBSERVED IN BM33-04.IMMEDIATE STABILIZATION AND REPAIR ARE REQUIRED FOR STRUCTURAL CRACKING IN BM33-04.REMEDY:IMMEDIATELY STABILIZE AND REPAIR BM33-04 UNDER FULL- TIME NYS PE,SIA,SSM AND CS.SIGNED AND SEALED SKETCHES ARE REQUIRED.AN APP MUST BE OPEN TO REFLECT SHORING REPAIR W/IN 2DAYS OF COMMENCEMENT
- Construction
Issued Jul 27, 2026 — PEER REVIEW-DEPT ORDERING A PEER REVIEW OF THE STRUCTURAL DESIGN & RELEVANT,ASSOCIATED SPECIAL REPORTS/SHOP DRAWINGS.TWO 14X48BEAMS EXHIBITED SIGNS OF SHEAR FAILURE.ONE 18X54 BEAM WAS OBSERVED TO HAVE SIGNS OF FLEXURE FAILURE.REMEDY:PROVIDE NAMES OF 3 NYS PE'S BY 8/5/26 SUBMIT PEER REVIEW REPORT PURSUANT TO BC 1618 BY 8/24/26
- Construction
Issued Jul 27, 2026 — AT THE TIME OF INSPECTION:OBSERVED A CRACK OCCURED AT BOTTOM OF MIDDLE 18X54CONCRETE BEAM AT EMR FLOOR.THE STRUCTURAL FAILURE REPRESENTS A POTENTIAL HAZARD TO THE PUBLIC.REMEDY:IMMEDIATELY DEVELOP&IMPLEMENT MONITORING PROTOCOL:OPTICAL MONITORING 2XWEEK-CRACK MONITOR 2XWEEK- MANDATE WEEKLY REPORT TO DOB.CEU NEEDS ALL INFO STARTING 7/26/26
2 further open notices are on file. Open the source dataset for the full list.
Open means the agency has not recorded a resolution, which is not the same as the problem still existing. What a violation is, and what it is not. From NYC Department of Buildings, DOB Violations (3h2n-5cm9), accessed Sep 25, 2026.
Recorded timeline
Dates published by the Department of Buildings.
- Application filed01
DOB received filing M01441217-I1.
- Application approved02
The application reached an approved status in the DOB record.
- Current status updated03
The latest recorded filing status is “Approved.”
For scale: half of DOB filings are permitted within 21 days of being filed and a quarter take longer than 4 months, measured across 69,387 filings that carry both dates. How long a permit takes, by work type and borough
Scope and identifiers
The details used to match this filing.
Where a field reads “empty in the source”, the city published this filing without that value. It is not an omission on our side, and nothing here is inferred to fill a gap.
- DOB filing number
- M01441217-I1
- BBL
- 1000890012
- Postal code
- 10038 · 180 filings
- Review type
- Standard Plan Examination
- Existing stories
- 31
- Proposed stories
- 32
- Existing dwelling units
- 0
- Proposed dwelling units
- 788