The lot
The lot holds a 14-story elevator apartment building built in 1948, with 591 homes, on a 323,438 sq ft lot.
Housing violations
9 violations are open against this address under the Housing Maintenance Code.
Open means the Department of Housing Preservation and Development has not recorded it as corrected, which is not the same as nobody having fixed it. The city publishes the apartment each was written against; that is not carried here, because a count says a building has a problem and an apartment number says whose.
Lot facts come from NYC Department of City Planning, Primary Land Use Tax Lot Output (PLUTO) (64uk-42ks), accessed Sep 21, 2026. They describe the tax lot, not any single filing. When the rest of New York went up
Violation record
The Department of Buildings has 4 open notices on record for this building, out of 23 notices on file; the most recent was issued Jun 2, 2025.
Issued Jun 2, 2025 — FAILURE TO MAINTAIN BUILDING EXTERIOR FACADE IN A CODE COMPLIANT MANNER. AT TIME OF INSPECTION IT WAS OBSERVED BALCONIES AT EXOSURES 1 & 3 (WEST & EAST ELEVATION) CRACKED, SPALLING AND EXPOSED REBARS AT MULTIPLE LOCATION. REMEDY: REPAIR AND/OR REPLACE
Issued May 14, 2025 — PARTIAL VACATE ORDER:OBSERVED CRACKED/SPALLED UNDERSIDE CONCRETE SLAB BALCONY AT EXPO 1 & 3, WEST & EAST ELEVATION OF ALL BALCONY LINES REMEDY: VACATE ALL BALCONY AT ALL 4 EXPOSURES, WEST, NORTH, EAST & SOUTH ELEVATIONS
Issued Feb 24, 2021 — NYCHA CYCLE 8A FAILURE TO CORRECT SWARMP CONDITIONS
1 further open notice is on file. Open the source dataset for the full list.
Open means the agency has not recorded a resolution, which is not the same as the problem still existing. What a violation is, and what it is not. From NYC Department of Buildings, DOB Violations (3h2n-5cm9), accessed Sep 21, 2026.
What is recorded here
New York City's Building Identification Number helps connect filings that may use different application numbers or describe different scopes of work. The records below are grouped because they publish BIN 3328126. They should not be read as a single construction project unless the underlying filings say so.
The matched set includes 16 alteration filing. Its latest status categories are 9 recorded as completed, 6 approved, 1 closed or withdrawn. Each filing page preserves its own status, dates, scope and source identifier.
Highest recorded values may come from different filings and must not be combined into one proposed project. Open the individual filings below for their exact scope. Values outside the publication's conservative data-quality bounds are withheld pending source review.
Address alerts
Get an email when NewYorkDaily detects a material change in the public DOB records associated with 430 Dumont Avenue.
Confirmation is required. Alerts describe source-data changes, not confirmed construction activity. Unsubscribe at any time. Privacy
Recorded history
Every dated event the city has published for this building, from all 16 matched filings, in the order it was recorded. A date marks what entered the public record, not what happened on site.
Installation of new sidewalk shed at 430 dumont avenue as indicated on plans. there will be no change in the use, egress, or occupancy under this application. Filing B00148159-I1.
DOB lists a first permit date for B00148159-I1. That is not by itself confirmation of activity on site.
Modifications to existing SP system at cellar, install new 15 sp heads, 1 new control valve at cel. Filing B00214579-I1.
Filing B00214579-I1 reached an approved status.
Project involves the installation of an on site storm water drainage retention system. the system uses underground chambers to temporarily store flow in accordance with the NYC dep green infrastructure program. Filing B00289745-I1.
Installation of temporary construction fence at 430 dumont avenue, brooklyn as indicated on plans. there will be no change in the use, egress, or occupancy under this application. Filing B00353111-I1.
Filing B00353111-I1 reached an approved status.
DOB lists a first permit date for B00353111-I1. That is not by itself confirmation of activity on site.
Filing B00289745-I1 reached an approved status.
Project involves the installation of on site storm water drainage retention systems. The systems use underground chambers to temporarily store flow in accordance with the NYC DEP Green Infrastructure Program. Filing B00481598-I1.
Project involves the installation of on site storm water drainage retention systems. The systems useunderground chambers to temporarily store flow in accordance with the nyc dep green infrastructure program. Filing B00487371-I1.
Filing B00487371-I1 reached an approved status.
Project involves the installation of an on site storm water drainage retention system. the system uses underground chambers to temporarily store flow in accordance with the NYC dep green infrastructure program. Filing B00289745-P1.
Filing B00481598-I1 reached an approved status.
Filing B00289745-P1 reached an approved status.
The latest status recorded for B00289745-P1 is “Approved.”
Mechanical work for central boiler plant and domestic hot water system replacement (van dyke bldg #23) as per the plans filed herewith. Filing B00463467-I1.
Nycha boiler- plumbing work as per plans filed herewith. no change to use, egress or occupancy. Filing B00463123-I1.
Filing B00463467-I1 reached an approved status.
General construction in the cellar as per plans filed herewith. no change to use, egress, or occupancy. Filing B00458429-I1.
Filing B00458429-I1 reached an approved status.
DOB lists a first permit date for B00289745-I1. That is not by itself confirmation of activity on site.
DOB lists a first permit date for B00481598-I1. That is not by itself confirmation of activity on site.
Installation of temporary construction fence 200 lf, at 430 dumont avenue, brooklyn, as indicated on plans. there will be no change in the use, egress, or occupancy under this application. Filing B00535600-I1.
Filing B00535600-I1 reached an approved status.
DOB lists a first permit date for B00535600-I1. That is not by itself confirmation of activity on site.
DOB lists a first permit date for B00487371-I1. That is not by itself confirmation of activity on site.
Nycha boiler-structrual work in the cellar floor as per plans filed herewith. no change in use, egress or occupancy. Filing B00461906-I1.
Filing B00461906-I1 reached an approved status.
Filing B00463123-I1 reached an approved status.
Installation of temporary construction fence as per plans filed herewith. no change to use, egress or occupancy. Filing B00587591-I1.
DOB lists a first permit date for B00587591-I1. That is not by itself confirmation of activity on site.
Installation of temporary construction fence as per plans filed herewith. no change to use, egress or occupancy. Filing B00587591-P1.
Filing B00587591-P1 reached an approved status.
The latest status recorded for B00587591-P1 is “Approved.”
DOB recorded a sign-off for B00587591-I1.
The latest status recorded for B00587591-I1 is “LOC Issued.”
DOB recorded a sign-off for B00289745-I1.
The latest status recorded for B00289745-I1 is “LOC Issued.”
DOB recorded a sign-off for B00487371-I1.
The latest status recorded for B00487371-I1 is “LOC Issued.”
DOB recorded a sign-off for B00481598-I1.
The latest status recorded for B00481598-I1 is “LOC Issued.”
DOB recorded a sign-off for B00535600-I1.
The latest status recorded for B00535600-I1 is “LOC Issued.”
DOB lists a first permit date for B00463467-I1. That is not by itself confirmation of activity on site.
DOB lists a first permit date for B00458429-I1. That is not by itself confirmation of activity on site.
DOB lists a first permit date for B00463123-I1. That is not by itself confirmation of activity on site.
DOB lists a first permit date for B00461906-I1. That is not by itself confirmation of activity on site.
Nycha boiler- plumbing work as per plans filed herewith. no change to use, egress or occupancy. Filing B00463123-P1.
Filing B00463123-P1 reached an approved status.
The latest status recorded for B00463123-P1 is “Approved.”
The latest status recorded for B00461906-I1 is “Permit Entire.”
DOB recorded a sign-off for B00148159-I1.
DOB recorded a sign-off for B00353111-I1.
The latest status recorded for B00148159-I1 is “LOC Issued.”
The latest status recorded for B00353111-I1 is “LOC Issued.”
The latest status recorded for B00214579-I1 is “Filing Withdrawn.”
Nycha boiler- plumbing work as per plans filed herewith. no change to use, egress or occupancy. Filing B00463123-P2.
The latest status recorded for B00463123-I1 is “Permit Entire.”
Filing B00463123-P2 reached an approved status.
The latest status recorded for B00463123-P2 is “Approved.”
DOB recorded a sign-off for B00458429-I1.
The latest status recorded for B00458429-I1 is “LOC Issued.”
DOB recorded a sign-off for B00463467-I1.